%20(500%20%C3%97%20280%20px)%20(500%20x%20300%20px)%20(33).png)
- This MoU aims to develop a 200 MW solar project in Dhar, along with a 1000 MWh battery storage project.
- Phase-wise Capital Investment: ₹2500 crore will be invested in phases for renewable energy expansion.
- Power Supply Agreement: A 25-year power supply agreement has been established with MP Power Management Company Limited (MPPMCL).
- Renewable Energy Expansion: The project is part of efforts to boost renewable energy capacity in Madhya Pradesh and contribute to sustainable development goals.
Question:
Q.1 What is the total planned capacity of the solar project under the MoU between Solar Energy Corporation of India (SECI) and Madhya Pradesh?a) 100 MW
b) 150 MW
c) 200 MW
d) 500 MW
Answer: c) The MoU aims to develop a 200 MW solar project in Dhar, Madhya Pradesh, along with a 1000 MWh battery storage project, contributing to the state's renewable energy goals.