- The project will have a capacity of 180 MW / 360 MWh and is designed to support grid stability, manage peak electricity demand, and enable greater integration of renewable energy sources like solar and wind.
- The funding includes $38.5 million from IFC’s own account and $16.5 million from the Clean Technology Fund (CTF).
- This initiative aligns with India’s national goal of achieving 500 GW of clean energy capacity by 2030 and Gujarat’s target of 100 GW renewable capacity.
- The project has received tariff approval from the Gujarat Energy Regulatory Commission (GERC) and is expected to be commissioned within FY 2025–26.
Question:
Q.1 On July 3, 2025, which organization committed ₹460 crore to support India’s largest standalone Battery Energy Storage System (BESS) project?a) Asian Development Bank (ADB)
b) International Finance Corporation (IFC)
c) Green Climate Fund (GCF)
d) World Economic Forum (WEF)
Answer: b) International Finance Corporation (IFC) a member of the World Bank Group, committed ₹460 crore ($55 million) to develop India's largest standalone BESS in Gujarat.